DEI was awarded the project in the spring of 2012 by Huntington Controls to provide installation of an energy management system for the AH1+AH4 buildings.
This comprised of low voltage control point & power wiring and a network+power loop per Huntington Controls design for all pertinent mechanical+electrical equipment.
AH4 building was a 4 story ground up new construction that contains offices, conference rooms, and a cafe.
AH1 was a 3 story existing building that was remodeled with new equipment for offices, conference rooms, a data center, and a fitness center.
Equipment By Building
AH1
- 3 RTU’s
- 3 Boilers & associated hot water pumps
- 4 CRAHU’s
- 2 Main Switchboard monitoring
- 2 UPS monitoring
- 4 PDU monitoring
- 200+ Cooling Beams
- 100+ VAV Boxes
- Miscellaneous exhaust fans, unit heaters, and split systems
AH4
- 3 RTU’s
- 3 Chillers & associated chilled water pumps
- 2 Cooling Towers+associated condenser water pumps
- 4 Heat recovery microturbines
- Kitchen exhaust+hood systems
- 700+ cooling beams
- 200+ VAV Boxes
- Miscellaneous exhaust fans, unit heaters, split units, and heat pumps